De La Salle North Catholic High School
Scope of work underway by Ward-Henshaw at the site in north Portland includes new concrete foundations and concrete slab for the gymnasium addition, concrete slab infill required at plumbing trenches, concrete curbs and walks, and extensive seismic improvements throughout the existing facility. The competitively bid project is valued at $4.4M. All work will be completed in Spring 2021.